GCPM · Question #144

In which of the following processes are the results of executing the quality activities recorded and monitored in order to assess performance and recommend necessary changes?

The correct answer is A. Perform Quality Control. See the full explanation below for the reasoning.

Question

In which of the following processes are the results of executing the quality activities recorded and monitored in order to assess performance and recommend necessary changes?

Options

  • APerform Quality Control
  • BPlan Quality
  • CControl Cost
  • DPerform Quality Assurance

How the community answered

(29 responses)
  • A
    76% (22)
  • B
    3% (1)
  • C
    14% (4)
  • D
    7% (2)