The correct answer is B. Critical chain method. See the full explanation below for the reasoning.
Question
Tom is the project manager for his organization and he's creating a project network diagram for this project. He has created his project network diagramming with the consideration of the availability of project resources. What network diagramming approach has Tom used in this example?
Options
- ACritical path method
- BCritical chain method
- CActivity on the arrow
- DFast tracking