Virginia is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter…

The correct answer is B. To determine the level of probability and impact for each risk event. See the full explanation below for the reasoning.

Question

Virginia is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter expert will assess the risk event with what specific goal in mind?

Options

  • ATo determine the probability and schedule of the risk event
  • BTo determine the level of probability and impact for each risk event
  • CTo determine the validity of each risk event
  • DTo determine the bias of the risk event based on each person interviewed

How the community answered

(52 responses)
  • A
    12% (6)
  • B
    81% (42)
  • C
    6% (3)
  • D
    2% (1)