Which of the following are outputs of the Perform Quality Control process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is B. Validated deliverables C. Validated changes D. Project document updates. See the full explanation below for the reasoning.

Question

Which of the following are outputs of the Perform Quality Control process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AQuality metrics
  • BValidated deliverables
  • CValidated changes
  • DProject document updates

How the community answered

(30 responses)
  • A
    23% (7)
  • B
    77% (23)

Community Discussion