GIAC
GCPM · Question #106
projects vary in size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can compare relative schedule and cost performance of each project. Which of the…
The correct answer is A. CPI and SPI. See the full explanation below for the reasoning.
Question
projects vary in size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can compare relative schedule and cost performance of each project. Which of the following components of EVM provide measures of schedule and cost performance that are not affected by the size of the project?
Options
- ACPI and SPI
- BBAC and EAC
- CPV and EV
- DCV and SV
How the community answered
(62 responses)- A79% (49)
- B5% (3)
- C13% (8)
- D3% (2)
Community Discussion
No community discussion yet for this question.