You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an…

The correct answer is B. Work breakdown structure. See the full explanation below for the reasoning.

Question

You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?

Options

  • AProject management plan
  • BWork breakdown structure
  • CCode of accounts
  • DProject scope

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    81% (29)
  • C
    11% (4)
  • D
    3% (1)