The correct answer is D. Analogous. See the full explanation below for the reasoning.

Question

durations for her project. She is using parameters such as duration, budget, size, weight, and complexity from a previous similar project as the basis for estimating the new project. Which of the following estimate activity duration techniques is she using in the project?

Options

  • AExpert judgment
  • BThree-point
  • CParametric
  • DAnalogous

Community Discussion

No community discussion yet for this question.

Full GCPM Practice