The Supplier Management process must define several formal policies and procedures to cover possible events in the service provider-supplier relationship. According to ISO/IEC 20000-1, what would not be defined?
Options
- AComplaints procedure
- BContractual disputes
- CEarly termination of the contract
- DTransferof service
How the community answered
(43 responses)- A70% (30)
- B16% (7)
- C5% (2)
- D9% (4)