The rollout of an application software upgrade has been planned. However, a back-out plan has not been developed. Which process or function should have provided the back-out plan?
The correct answer is C. Release management. See the full explanation below for the reasoning.
Question
The rollout of an application software upgrade has been planned. However, a back-out plan has not been developed. Which process or function should have provided the back-out plan?
Options
- AAvailability management
- BChange management
- CRelease management
- DService desk
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C75% (21)
- D14% (4)