Through which process does the implementation of a new or changed service, including closure of a service, need to be planned and approved?

The correct answer is B. Change management. See the full explanation below for the reasoning.

Question

Through which process does the implementation of a new or changed service, including closure of a service, need to be planned and approved?

Options

  • ABusiness relationship management
  • BChange management
  • CRelease management
  • DService level management

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    70% (21)
  • C
    7% (2)
  • D
    17% (5)