The effects of a disaster on IT services can be severe. Measures should be taken to prevent, detect, prepare for and mitigate these effects. Which process is responsible for taking these measures?
The correct answer is C. Service continuity management. See the full explanation below for the reasoning.
Question
The effects of a disaster on IT services can be severe. Measures should be taken to prevent, detect, prepare for and mitigate these effects. Which process is responsible for taking these measures?
Options
- AAvailability management
- BInformation security management
- CService continuity management
- DService level management
How the community answered
(16 responses)- A13% (2)
- B6% (1)
- C75% (12)
- D6% (1)