A Post implementation review (PIR) is used to determine whether a corrective change has been successfully implemented. Which process works in conjunction with Change management during a PIR?
The correct answer is A. Problem management. See the full explanation below for the reasoning.
Question
A Post implementation review (PIR) is used to determine whether a corrective change has been successfully implemented. Which process works in conjunction with Change management during a PIR?
Options
- AProblem management
- BConfiguration management
- CRelease management
- DCapacity management
How the community answered
(25 responses)- A80% (20)
- B4% (1)
- C4% (1)
- D12% (3)