When considering risks, which describes an opportunity in a project?
The correct answer is B. An uncertain event that could have a favourable impact on objectives. See the full explanation below for the reasoning.
Question
When considering risks, which describes an opportunity in a project?
Options
- AAn uncertain event that could have a negative impact on objectives
- BAn uncertain event that could have a favourable impact on objectives
- CAn event that has occurred resulting in a negative impact on objectives
- DAn event that has occurred resulting in a favourable impact on objectives
How the community answered
(23 responses)- A9% (2)
- B74% (17)
- C13% (3)
- D4% (1)
Community Discussion