The correct answer is B. Project Initiation Documentation. See the full explanation below for the reasoning.

Question

What product forms the contract' between the Project Board and the Project Manager?

Options

  • AProject Brief
  • BProject Initiation Documentation
  • CProject mandate
  • DProject Plan