Which of the following is NOT part of quality planning?
The correct answer is B. Gain acceptance of the project product. See the full explanation below for the reasoning.
Question
Which of the following is NOT part of quality planning?
Options
- ADefine quality responsibilities
- BGain acceptance of the project product
- CAgree acceptance criteria
- DSet quality tolerances
How the community answered
(42 responses)- A12% (5)
- B81% (34)
- C5% (2)
- D2% (1)