What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?

The correct answer is C. Having insufficient time to perform the role. See the full explanation below for the reasoning.

Question

What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?

Options

  • AThe preference of the Project Manager
  • BHaving insufficient authority to perform the role
  • CHaving insufficient time to perform the role
  • DThe need to involve key stakeholders on the project management team

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    8% (2)
  • C
    75% (18)
  • D
    4% (1)