EX0-002 · Question #89
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
The correct answer is B. Follow-on action recommendations. See the full explanation below for the reasoning.
Question
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Options
- AOff-specifications
- BFollow-on action recommendations
- CIssue Register
- DRisk Register
How the community answered
(31 responses)- A3% (1)
- B84% (26)
- C10% (3)
- D3% (1)