EX0-002 · Question #88

Which describes risk probability?

The correct answer is D. A measure of the likelihood of the risk occurring. See the full explanation below for the reasoning.

Question

Which describes risk probability?

Options

  • ALevel of risks which the project can tolerate before escalating to the Project Board
  • BProbable effect on the project delivering its objectives
  • CTimeframe within which the risk may occur
  • DA measure of the likelihood of the risk occurring

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    3% (1)
  • C
    6% (2)
  • D
    79% (27)