Which is NOT a requirement of a Stage Plan?

The correct answer is C. Approved and signed-off by Project Assurance. See the full explanation below for the reasoning.

Question

Which is NOT a requirement of a Stage Plan?

Options

  • AProduced to an appropriate level of detail to enable day-to-day control
  • BProduced near to the end of the previous management stage
  • CApproved and signed-off by Project Assurance
  • DApproved at the end of a management stage

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    81% (22)
  • D
    11% (3)