EX0-002 · Question #93
EX0-002 Question #93: Real Exam Question with Answer & Explanation
Sign in or unlock EX0-002 to reveal the answer and full explanation for question #93. The question stem and answer options stay visible for context.
Question
Which of the following statements about lines of authority and reporting are true? 1. The Project Manager has day-to-day control for a management stage within the limits Laid. 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Options
- AOnly 1 is true
- BOnly 2 is true
- CBoth 1 and 2 are true
- DNeither 1 or 2 are true
Unlock EX0-002 to see the answer