EX0-002 · Question #4
Which should be funded by a change budget?
The correct answer is A. Increase in agreed scope. See the full explanation below for the reasoning.
Question
Which should be funded by a change budget?
Options
- AIncrease in agreed scope
- BInitiation stage
- CChange Authority
- DHandover activities
How the community answered
(44 responses)- A84% (37)
- B9% (4)
- C2% (1)
- D5% (2)