EX0-002 · Question #3

Which is an objective of the Starting up a Project process?

The correct answer is A. Identify who will be responsible for creating the Project Plan. See the full explanation below for the reasoning.

Question

Which is an objective of the Starting up a Project process?

Options

  • AIdentify who will be responsible for creating the Project Plan
  • BAgree how the project will be monitored and controlled after initiation
  • CAuthorize the Project Manager to proceed with the initiation stage
  • DAgree how issues and changes will be identified, assessed and controlled

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    8% (2)
  • C
    4% (1)
  • D
    12% (3)