The correct answer is C. Record the change in a product's status. See the full explanation below for the reasoning.

Question

Which of the following describes a use of a Configuration Item Record?

Options

  • ADefine the identification scheme to be applied to the project
  • BIdentify the techniques and procedures required within the Work Package
  • CRecord the change in a product's status
  • DRecord the reporting requirements for the Work Package