PMI
DASSM · Question #165
A team is about to begin work on a project that will face rapidly changing with releases only every six months or so. The team does not have an agile mindset, and does not want to release often…
The correct answer is D. Lean. See the full explanation below for the reasoning.
Question
A team is about to begin work on a project that will face rapidly changing with releases only every six months or so. The team does not have an agile mindset, and does not want to release often. Which lifecycle should the scrum master select?
Options
- AAgile
- BTraditional
- CProgram
- DLean
How the community answered
(19 responses)- B5% (1)
- C11% (2)
- D84% (16)
Community Discussion
No community discussion yet for this question.