DASSM · Question #164
In Team Estimation...
The correct answer is A. You first estimate the relative sizes of all stories, then assign numbers to them. See the full explanation below for the reasoning.
Question
In Team Estimation...
Options
- AYou first estimate the relative sizes of all stories, then assign numbers to them.
- BEach team is ranked in order of importance for completing a task.
- CMembers of a group define what criteria will be used for determining the "Definition of Done".
- DYou estimate what roles will be necessary in order to complete user stories.
How the community answered
(35 responses)- A80% (28)
- B6% (2)
- C11% (4)
- D3% (1)