DASSM · Question #153

When should an iteration backlog be created?

The correct answer is D. At the beginning of each sprint.. See the full explanation below for the reasoning.

Question

When should an iteration backlog be created?

Options

  • AAt the beginning of each project.
  • BWhen defining the MBI (Minimum Business Increment).
  • CWhen planning the Kanban board or other pull method.
  • DAt the beginning of each sprint.

How the community answered

(19 responses)
  • A
    5% (1)
  • C
    11% (2)
  • D
    84% (16)