The team lead notices that a team member is falling behind on their work. What would a good Disciplined Agile team lead do?
The correct answer is B. Have a conversation with the team member to better understand what is getting in their way and. See the full explanation below for the reasoning.
Question
The team lead notices that a team member is falling behind on their work. What would a good Disciplined Agile team lead do?
Options
- AProvide time management training to the team member.
- BHave a conversation with the team member to better understand what is getting in their way and
- CHave a one-to-one meeting with the team member about their recent failures.
- DRedistribute the team member's work across the team to avoid embarrassing the team member.
How the community answered
(23 responses)- A9% (2)
- B74% (17)
- C13% (3)
- D4% (1)