Your team wants to work in an Agile manner and has been asked to provide a cost estimate for the project even though management recognizes that the requirements will evolve overtime. Which process goal is most likely to offer potential techniques to address this?
Options
- AProject Management
- BPlan the Release
- CExplore Scope
- DAddress Changing Stakeholder Needs