For an Agile or Lean project team, which best describes the aim of the Inception phase?
The correct answer is D. The team performs sufficient work to initiate the endeavor and obtain agreement as to the overall. See the full explanation below for the reasoning.
Question
For an Agile or Lean project team, which best describes the aim of the Inception phase?
Options
- AThe team develops a plan to build a minimum business increment (MBI) that meets the needs of
- BThe team performs sufficient work to develop a plan for performing initial requirements modeling,
- CThe team develops a plan to build a consumable solution that meets the needs of their
- DThe team performs sufficient work to initiate the endeavor and obtain agreement as to the overall
How the community answered
(37 responses)- A3% (1)
- B14% (5)
- C5% (2)
- D78% (29)