Which of the following may not help in improving predictability?
The correct answer is A. Estimate in hours instead of points. See the full explanation below for the reasoning.
Question
Which of the following may not help in improving predictability?
Options
- AEstimate in hours instead of points
- BReduce technical debt
- CReduce feedback cycles
- DRespect WIP limits
- EAdopt a test-first approach
How the community answered
(20 responses)- A70% (14)
- C5% (1)
- D10% (2)
- E15% (3)
Community Discussion