Which of the following is not a responsibility of the team members in a disciplined agile team?

The correct answer is A. Set appropriate expectations about release timings with the customer. See the full explanation below for the reasoning.

Question

Which of the following is not a responsibility of the team members in a disciplined agile team?

Options

  • ASet appropriate expectations about release timings with the customer
  • BSelf-organize
  • CEvolve their way of working
  • DEvolve the architecture with help of architecture owner

How the community answered

(42 responses)
  • A
    81% (34)
  • B
    2% (1)
  • C
    12% (5)
  • D
    5% (2)