The Kaizen feedback loop can be summarized as:
The correct answer is D. Plan, Do, Study, Act. See the full explanation below for the reasoning.
Question
The Kaizen feedback loop can be summarized as:
Options
- APlan, Do, Monitor, Study
- BStudy, Act, React, Demo
- CPlan, Implement, Demo, Study
- DPlan, Do, Study, Act
How the community answered
(45 responses)- A4% (2)
- B7% (3)
- C11% (5)
- D78% (35)