ASQ
CSSGB · Question #165
CSSGB Question #165: Real Exam Question with Answer & Explanation
The correct answer is D. longest path from the start to the completion of the project. See the full explanation below for the reasoning.
Question
The critical path for a project is best described as the
Options
- Asequence of steps with the highest costs
- Btasks in the project that have the highest risk of failure
- Csum of the tasks with the shortest time requirements
- Dlongest path from the start to the completion of the project
Community Discussion
No community discussion yet for this question.