The critical path for a project is best described as the
The correct answer is D. longest path from the start to the completion of the project. Critical path refers to the longest sequence of dependent tasks from project start to finish - option D - because it determines the minimum total time needed to complete the project; any delay on this path directly delays the entire project. Option A is wrong because cost has…
Question
The critical path for a project is best described as the
Options
- Asequence of steps with the highest costs
- Btasks in the project that have the highest risk of failure
- Csum of the tasks with the shortest time requirements
- Dlongest path from the start to the completion of the project
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C7% (2)
- D85% (23)
Explanation
Critical path refers to the longest sequence of dependent tasks from project start to finish - option D - because it determines the minimum total time needed to complete the project; any delay on this path directly delays the entire project.
Option A is wrong because cost has no bearing on the critical path - expensive tasks can have plenty of float and never appear on it. Option B is wrong because risk level is irrelevant; low-risk, routine tasks can be on the critical path. Option C is wrong because it's the longest path, not the shortest - tasks with the shortest durations often have slack and aren't critical at all.
Memory tip: Think of the critical path as the bottleneck highway - it's the longest route you must travel, and a traffic jam anywhere on it holds up the whole trip.