nerdexam
ASQ

CSSGB · Question #165

CSSGB Question #165: Real Exam Question with Answer & Explanation

The correct answer is D. longest path from the start to the completion of the project. See the full explanation below for the reasoning.

Question

The critical path for a project is best described as the

Options

  • Asequence of steps with the highest costs
  • Btasks in the project that have the highest risk of failure
  • Csum of the tasks with the shortest time requirements
  • Dlongest path from the start to the completion of the project

Community Discussion

No community discussion yet for this question.

Full CSSGB Practice