CSM-001 · Question #90
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
The correct answer is C. This forces Product Owners to focus on what is really important for the team to develop. See the full explanation below for the reasoning.
Question
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
Options
- AThe development team cannot meet their Sprint commitment to complete work if requirements
- BA Sprint cycle is not enough time for senior management review and approve changes
- CThis forces Product Owners to focus on what is really important for the team to develop.
- DThe development team must be able to limit the Product Owner authority
How the community answered
(29 responses)- A10% (3)
- B14% (4)
- C72% (21)
- D3% (1)