Which of the following statements best explains what the term Sprint means in Scrum?
The correct answer is B. A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work. See the full explanation below for the reasoning.
Question
Which of the following statements best explains what the term Sprint means in Scrum?
Options
- AA sprint is a specific amount of days for a team to test and resolve any issues prior to product
- BA sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.
- CA sprint is an agreed upon period of time for team members to select individual items from the
- DA sprint is a specific amount of days for a team to work as many hours as needed to finish
How the community answered
(19 responses)- A5% (1)
- B84% (16)
- C5% (1)
- D5% (1)