Question
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with thefollowing information:
Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14 pontos Sprint 5: 15 pontos Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number ofSprintrequired to complete product development?
Options
- A6
- B5
- C4
- D3
How the community answered
(15 responses)- A7% (1)
- B80% (12)
- D13% (2)