nerdexam
GAQM

CSM-001 · Question #109

You are the Scrum Master and your Development Team of 6 members has completed six Sprints with thefollowing information: Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14…

The correct answer is B. 5. See the full explanation below for the reasoning.

Question

You are the Scrum Master and your Development Team of 6 members has completed six Sprints with thefollowing information:

Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14 pontos Sprint 5: 15 pontos Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number ofSprintrequired to complete product development?

Options

  • A6
  • B5
  • C4
  • D3

How the community answered

(15 responses)
  • A
    7% (1)
  • B
    80% (12)
  • D
    13% (2)

Community Discussion

No community discussion yet for this question.

Full CSM-001 Practice