CSM-001 · Question #146
During the daily standup meeting, a team member states that an issue has been encountered. This leads to the team members getting into a problem-solving discussion. How would the Scrum Master respond?
The correct answer is A. Ask the team members to table the discussion until after the meeting is over. Certified Scrum Master (CSM) LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you…
Question
During the daily standup meeting, a team member states that an issue has been encountered. This leads to the team members getting into a problem-solving discussion. How would the Scrum Master respond?
Options
- AAsk the team members to table the discussion until after the meeting is over
- BIf the item is really important, allow the discussion to expedite resolution of the issue
- CAbruptly end the daily standup meeting and schedule another meeting to discuss the issue
- DAsk the team how they would like to use the daily standup meeting for that day
How the community answered
(44 responses)- A70% (31)
- B18% (8)
- C7% (3)
- D5% (2)
Explanation
Certified Scrum Master (CSM) LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.