According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?

The correct answer is C. Hours. See the full explanation below for the reasoning.

Question

According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?

Options

  • AWeeks
  • BDays
  • CHours
  • DMinutes

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    76% (16)
  • D
    14% (3)