The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
The correct answer is D. Tasks. See the full explanation below for the reasoning.
Question
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
Options
- AUser Stories
- BUse cases
- CLine items
- DTasks
How the community answered
(37 responses)- A5% (2)
- B11% (4)
- C3% (1)
- D81% (30)