GAQM
CSM-001 · Question #62
When many Scrum Teams are working on the same product, should all of their increments be integrated everySprint?
The correct answer is D. Yes, otherwise Product Owners may not be able to inspect what is done accurately. See the full explanation below for the reasoning.
Question
When many Scrum Teams are working on the same product, should all of their increments be integrated everySprint?
Options
- ANo, that is far too hard
- BNo, each Scrum Team stands alone
- CYes, but only the Scrum's Teams whose work has dependencies
- DYes, otherwise Product Owners may not be able to inspect what is done accurately
How the community answered
(28 responses)- A7% (2)
- B11% (3)
- D82% (23)
Community Discussion
No community discussion yet for this question.