When many Scrum Teams are working on a project, what best describes the definition of "done"?
The correct answer is A. All teams must use the same definition. See the full explanation below for the reasoning.
Question
When many Scrum Teams are working on a project, what best describes the definition of "done"?
Options
- AAll teams must use the same definition
- BEach Team defines and uses its own
- CEach Team uses its own but must make it clear to all other Teams
- DIt depends
How the community answered
(54 responses)- A83% (45)
- B2% (1)
- C11% (6)
- D4% (2)