More than one Scrum Team is working on a single project or release. How should the Product Backlog bearranged?
The correct answer is B. All Scrum Teams work from a common Product Backlog and integrate their work every sprint. See the full explanation below for the reasoning.
Question
More than one Scrum Team is working on a single project or release. How should the Product Backlog bearranged?
Options
- AA separate Product Backlog is constructed for each Scrum Team. All of the increments are
- BAll Scrum Teams work from a common Product Backlog and integrate their work every sprint
- COnly one Scrum Team should work on Scrum project
- DScrum Teams should have their separate Product Backlogs
How the community answered
(55 responses)- A13% (7)
- B75% (41)
- C9% (5)
- D4% (2)