What is the primary responsibility of the Scrum Master?

The correct answer is B. To remove any impediments the Development Team encounters during their work. See the full explanation below for the reasoning.

Question

What is the primary responsibility of the Scrum Master?

Options

  • ATo Prioritize the Product Backlog
  • BTo remove any impediments the Development Team encounters during their work
  • CTo work with the Product Owner to develop the Product Backlog
  • DTo manage the Development Team

How the community answered

(21 responses)
  • B
    81% (17)
  • C
    5% (1)
  • D
    14% (3)