On a new Scrum Team, the Development Team tell the Scrum Master that theydon't feel the need forretrospectives.Which answer iscorrect?

The correct answer is C. None of above. See the full explanation below for the reasoning.

Question

On a new Scrum Team, the Development Team tell the Scrum Master that theydon't feel the need forretrospectives.Which answer iscorrect?

Options

  • ADiscuss with product owner
  • BStart doing retrospectives
  • CNone of above

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    13% (4)
  • C
    80% (24)