GAQM
CSM-001 · Question #129
The Product Backlog ismaintainedby:
The correct answer is C. The Product Owner. See the full explanation below for the reasoning.
Question
The Product Backlog ismaintainedby:
Options
- AThe Scrum Master
- BThe Development Team
- CThe Product Owner
- DThe Product Owner and Scrum Master
How the community answered
(52 responses)- A4% (2)
- B13% (7)
- C77% (40)
- D6% (3)
Community Discussion
No community discussion yet for this question.