CSM-001 · Question #127
Who is required to attend the Daily Scrum?
The correct answer is B. Development Team. See the full explanation below for the reasoning.
Question
Who is required to attend the Daily Scrum?
Options
- AScrum Master
- BDevelopment Team
- CDevelopment Team and Product Owner
- DDevelopment Team and Scrum Master
How the community answered
(25 responses)- A4% (1)
- B84% (21)
- C4% (1)
- D8% (2)