Which of the following is not a Scrum Master responsibility?

The correct answer is B. Preventing Senior Management from shifting team priorities. See the full explanation below for the reasoning.

Question

Which of the following is not a Scrum Master responsibility?

Options

  • AEstablish priorities together with product owner for Product Backlog items
  • BPreventing Senior Management from shifting team priorities
  • CEmpowering the team
  • DSocializing scrum throughout the organization

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    79% (27)
  • C
    12% (4)
  • D
    3% (1)