From the activities given, which is the latest step in sequence of the Scrum framework?

The correct answer is B. Sprint retrospective. See the full explanation below for the reasoning.

Question

From the activities given, which is the latest step in sequence of the Scrum framework?

Options

  • ADaily scrum
  • BSprint retrospective
  • CSprint review
  • DSprint planning

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    78% (31)
  • C
    15% (6)