Which of the following is reflected in a Sprint Burndown Chart?

The correct answer is D. Work Hours Remaining. See the full explanation below for the reasoning.

Question

Which of the following is reflected in a Sprint Burndown Chart?

Options

  • ATeam Members Name
  • BNumber of Product Backlog Items Completed
  • CNumber of Tasks Remaining
  • DWork Hours Remaining

How the community answered

(39 responses)
  • A
    18% (7)
  • B
    8% (3)
  • C
    3% (1)
  • D
    72% (28)