Who must always authorise a Request for Change before the change is built and tested?
The correct answer is C. The Change Manager. You've hit your limit · resets 12:50am (America/New_York)
Quality Management Systems
Question
Who must always authorise a Request for Change before the change is built and tested?
Options
- AThe Configuration Manager
- BThe Change Initiator
- CThe Change Manager
- DRelease Management
How the community answered
(24 responses)- B4% (1)
- C96% (23)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#Change Management#RFC authorization#Change Manager#change approval